TypeGoods
ProjectWestlands fit-out
Needed by14 Oct
Deliver toWestlands site, 3rd floor
ItemBudget lineQtyTotal
Gypsum board 12mmPartitions and ceilings220275,000
Steel studs 3mPartitions and ceilings360108,000
Ceiling grid, per roomPartitions and ceilings1029,000
Cable trunking 3mElectrical8036,000
Emulsion paint 20LFinishes and paint1254,000
Total · 5 items, 3 lines502,000
ReasonPhase 2 fit-out, 3rd floor
Budget check by line 1 of 3 over
Partitions and ceilingsOver by 34,000
Left 378,000 · this request 412,000
ElectricalFits · 84,000 left
Left 120,000 · this request 36,000
Finishes and paintFits · 42,000 left
Left 96,000 · this request 54,000
Partitions and ceilings is over
1Cut the boards to 200 to fit KES 378,000
2Request a supplementary budget of KES 34,000
Submit is blocked until every line fits